Wellfield Groundwater Demineralization

Zone 7 Water Agency
Project Type: 
Designer: 
Carollo Engineers
Contractor: 
GSE Construction
Construction Cost: 
$19.0 million

The project constructed the Mocho Groundwater Demineralization Plant which included a new reverse osmosis (RO) membrane demineralization plant capable of producing 6.1 mgd of permeate. The new demineralization plant included a building with cartridge filters, RO membrane feed pumps, RO membrane skids, decarbonation towers, chlorine contact basin, high service pumps, concentrate disposal pumps, chemical feed systems, membrane clean-in-place system, electrical room, storage room, control room, water quality station, and restroom.

Key Project Features: 
  • The treatment process includes Reverse Osmosis.