Altamont Creek – Arroyo Las Positas Channel
Zone 7 Water Agency
Project Type:
Designer:
Zone 7 Water Agency
Contractor:
Fanfa, Inc.
Construction Cost:
$595,000
This project consisted of desilting and channel restoration of approximately 2,000 linear feet along Altamont Creek and Arroyo Las Positas in the vicinity of Bluebell Drive. Work included replanting seeding along the channel, installation of fencing, gates, repaving approximately 1,500 linear feet of an asphalt concrete access road, construction of a grade control structure, and installation of rock slope protection.