The project includes the construction of a new 4.3 mgd average dry weather flow wastewater treatment plant. Work consists of integrating the existing wastewater treatment facilities, constructing an influent treatment pipeline from the existing wastewater treatment plant to the new wastewater treatment plant, installing a discharge pipeline, outfall, and diffuser off the north shore of Jersey Island for discharge of treated effluent into the San Joaquin River and extension of a 24-inch diameter pipeline on Jersey Island.
The Process Components include: influent sewer, influent pump station, influent metering, coarse screening, grit removal, process metering, fine screening, anoxic basins, transfer pumps, membrane filtration, permeate filtrate pumps, aeration and membrane blowers, ultraviolet disinfection facilities, utility water pump station, effluent pump station, effluent metering, solids handling, odor control facilities, standby power, effluent pipeline, and outfall.